How long does it take to install a GRP roof?

From Janet Sawood

Hello,

How long does it usually take for your fibreglass roof to be installed by an approved contractor?

A:

Hi Janet,

Factors like weather and temperature need to be taken into account when applying a fibreglass roof and preparation for the job is a key element. A team of two Allbase approved contractors should be able to re-deck and coat a roof of around 20 square metres in a working day.

Hope this helps, if you have any more questions please give us a call.